Free Motor Controls & PLCs practice questions

  1. 1.A 3-phase motor nameplate reads FLA 28A. What size overload heater is required?

    • A.28A✓
    • B.25A
    • C.30A
    • D.115% of FLA = 32.2A

    Why: Overloads are sized at or near FLA (Full Load Amps). Select the heater element from the manufacturer's table that corresponds to 28A. CEC allows up to 125% for standard motors.

  2. 2.A star-delta (wye-delta) starter reduces starting current by:

    • A.25%
    • B.33% (to 1/3 of DOL current)✓
    • C.50%
    • D.75%

    Why: Wye-delta starting reduces inrush to approximately 1/3 of direct-on-line (DOL) current. Motor starts in wye (lower voltage per winding) then switches to delta for full speed.

  3. 3.What does a PLC input module do?

    • A.Powers the motor
    • B.Converts field device signals to logic levels the CPU can process✓
    • C.Runs the program
    • D.Stores data long-term

    Why: Input modules interface field devices (switches, sensors, transmitters) to the PLC CPU by converting real-world signals to digital logic levels.

  4. 4.A motor drawing 45A on 2 phases and 0A on the third has:

    • A.Normal operation
    • B.A single-phasing condition (lost phase)✓
    • C.Excess load
    • D.A grounded conductor

    Why: Single-phasing (loss of one phase) causes remaining phases to carry excess current. The motor overheats rapidly. Phase loss relays protect against this.

  5. 5.What does a motor's service factor of 1.15 mean?

    • A.15% below rated power
    • B.The motor can safely run at 115% of rated HP continuously✓
    • C.The motor is 15% efficient
    • D.15% voltage tolerance

    Why: Service factor 1.15 means the motor can operate at 115% of nameplate HP without damage under rated conditions. It provides a safety margin but reduces motor life.

  6. 6.What is the advantage of a soft starter over a DOL starter?

    • A.Lower cost
    • B.Reduced starting current and mechanical stress on the driven equipment✓
    • C.Higher speed
    • D.Better for small motors only

    Why: Soft starters ramp voltage gradually, reducing inrush current and mechanical shock to belts, couplings, and driven equipment. Ideal for pumps, fans, and conveyors.

  7. 7.In a PLC timer instruction TON, the output is TRUE when:

    • A.Timer starts
    • B.The accumulated value equals or exceeds the preset value while input is TRUE✓
    • C.The input goes FALSE
    • D.The PLC powers up

    Why: TON (Timer On-Delay): output energizes after the accumulated time reaches the preset, AND the input remains TRUE. If input goes FALSE, the timer resets.

  8. 8.A reversing motor starter uses:

    • A.One contactor and a switch
    • B.Two mechanically and electrically interlocked contactors✓
    • C.Three contactors
    • D.A VFD only

    Why: Reversing starters have two contactors (forward/reverse) that swap two phases. Mechanical AND electrical interlocks prevent both from energizing simultaneously (dead short).

12 more Motor Controls & PLCs questions inside

Plus a timed 309A exam simulator, spaced-repetition review of every question you get wrong, and an AI tutor you can ask “why?”.

Start free — 20 questions a day →

Other 309A exam blocks

Occupational SkillsElectrical FundamentalsBranch Circuit WiringDistribution EquipmentSpecialty Systems

Other Red Seal trades

Industrial Electrician (442A)Plumber (306A)Steamfitter / Pipefitter (307A)Automotive Service Technician (310S)Carpenter (403A)Tool and Die Maker (430A)Industrial Mechanic (Millwright) (433A)Welder (456A)

RedSeal Prep Pro is an independent study tool. Practice questions are original content written in the style of the Certificate of Qualification and are not affiliated with the Red Seal Program, the Construction Electrician trade board, or any provincial certification body.